Florida Milestone Inspection Guide: 2026 Compliance

Understanding your building safety obligations under SB 154 and the HB 1021 accountability updates.

2026 Board Summary

  • 30-Year Trigger: Initial inspections are mandatory statewide at the 30-year mark (25 years if coastal).
  • The Two-Phase Process: Phase 1 is a non-invasive visual check; Phase 2 is only required if deterioration is found.
  • 10-Year Intervals: Subsequent inspections must be performed every decade to maintain legal occupancy.
  • Board Education: HB 1021 now requires directors to certify completion of safety and reserve training.

Phase 1 vs. Phase 2

Think of Phase 1 as a structural physical exam. If your engineer spots substantial rust, concrete spalling, or structural distress, Phase 2 is triggered to determine the full extent of the damage.

Request Milestone Inspection

Milestone FAQ

Buildings with fewer than three habitable stories are currently exempt from the statewide Milestone Inspection and SIRS requirements.